Mt Coot-tha Quarry History of Significant Events - 2015



2015
The Legacy Way construction began in April 2011. This project continued to emit loud noise both day and night until June 2015 when it was opened to traffic. This was in addition to the normal quarry Blasting.



5th May
Quarry lets rip with an extremely strong blast which shatters one of our patio balustrade glass panels.
Pieces of glass were spread over a 5m radius which took considerable time to clean-up.
Three glass panels had to be replaced before the area could be declared safe again.

5th May
Following on from Yesterdays very strong blast, we inspect our ground floor slab to find extremely long and 1mm wide cracks have increased in size.
Note that concrete shrinkage cracks of 1mm every 6 metres are common, but these cracks exceed those that would be caused by concrete shrinkage.
Further inspections at later dates have revealed increasing crack lengths and widths.
A subsequent inspection by a RPEQ mechanical engineer advised that the cracks appear to be formed in an unusual pattern, which could be due to the strong vibrations.

11th August
The Council let rip with an extremely strong quarry blast which had all our tradesmen thinking it was an earthquake.
A complaint was lodged regarding this with EHP and the Quarry Manager.

22nd October
Philip Best complains to LM Quirk about the extremely strong quarry blast.

4th November
LM Quirk replies to our previous complaint email letters.
He claims that each blast is independantly monitored and assessed by Heilig is not true. All Heilig does is place a transducer where and how the quarry manager says.

11th November
Philip Best complains to LM Quirk about his letter and the Blasting.

17th December
LM Quirk replies to our complaints regarding quarry operations.

Top of Page